    Phases laid out for outdoor sports complex

    The planned outdoor sports complex in Brandon is estimated to cost approximately $16 million to build, with a three-year construction schedule starting this fall, it was revealed at Monday’s Brandon City Council meeting. At the meeting, manager of parks operations Bryce Wilson delivered a progress update on the creation of the complex destined to be built east of First Street North and south of Veterans Way. The estimated price tag includes a 30 per cent contingency in case of unexpected costs or cost overruns. Phase 1 of the project, expected to start construction this year and continue next year, is supposed to cost around $6,726,000 with $8,743,800 being put aside…